Focusing on site clearance of Ton Duc Thang – Mang Nuoc Road grade-separating overpass
To achieve the goal of quickly putting into use the project of the intersection at Ton Duc Thang – Mang Nuoc - National Highway No. 5 in order to reduce traffic congestion and accidents, An Duong district needs to accelerate the site clearing process, hindered by obstacles while being implemented.

 Khởi công Nút giao khác mức tại ngã tư đường Tôn Đức Thắng - Máng Nước - Quốc lộ 5

 

Up to this point, An Duong District Construction and Investment Project Management Board has inventoried 140 households whose land is inside the reclaimed boundaries for the project with a total area of 3,000 m2. However, the pricing of the land has not yet been approved.

In the past few days, due to the lane separation for the construction, vehicles have been forced to change direction when turning into Mang Nuoc Road, thus putting pressure on Route 208. After the Nam Cau Binh (South of Binh Bridge) intersection comes into operation, this area became filled with intersection routes and crowded with transports, especially container trucks delivering cargoes to Hai Phong Port. The overpass construction project has a total investment of 689 billion VND, disbursed from the city's budget, built directly in the direction of National Highway No. 5 - Nguyen Van Linh Road. Therefore it is necessary to promptly speed up the progress so as to reduce traffic congestion or risks on Highway 5 as quickly as possible and correspond to people’s needs. /.


QR Code

Hai Phong Portal

Editor-in-chief: Chief of staff Hoang Van Thuc

Head office: Building B, City Political-Administrative Center, Thuy Nguyen Ward, Hai Phong City