Site clearance accelerated for road project
Hai Phong is accelerating site clearance for a project linking Provincial Road 354 in Tien Lang district with the National Highway 10 in Vinh Thuan commune. The project is managed by the Hai Phong Transport Construction Investment Project Management Board. Total land acquisition in Vinh Thuan commune covers 4.56 hectares.

Authorities have issued land recovery notices to all 161 households with agricultural land. They have also worked with consultants to determine land prices for compensation plans. Compensation plans have been approved for 147 households, with land acquisition decisions issued for 101 households.
Payments have been made to 138 of the 147 households. In the coming period, authorities will complete compensation plans for residential land in April. Appraisal and approval are scheduled for May. Resettlement arrangements, payments and site handover will then be implemented.

 

QR Code

Hai Phong Portal

Editor-in-chief: Chief of staff Hoang Van Thuc

Head office: Building B, City Political-Administrative Center, Thuy Nguyen Ward, Hai Phong City