Land acquisition for Lao Cai - Ha Noi - Hai Phong railway
Kien Minh Commune Party Committee has established a Steering Committee for site clearance to implement the Lao Cai-Hanoi-Hai Phong Railway Project.
The Steering Committee consists of 16 members, tasked with advising and leading the land acquisition; mobilizing related households, carrying out inventory, verification, resettlement arrangements, ensuring security and order, removing obstacles, urging progress
The Lao Cai-Hanoi-Hai Phong Railway Project section through Kien Minh Commune needs to revoke an area of 71.1 hectares with a total of 625 plots of land. To date, the commune has reviewed the land origin of more than 430 households, signed land map confirmations for 321 households; completed compensation plans for 152 households; inventoried 15.73 hectares of agricultural land and is going to review resettlement records for households whose residential land is revoked.