23/03/2012
5 projects invest in VSIP Haiphong
Such information was exposed at the
annual meeting, held on the
morning of 15th Marchfor reviewing the development progress of VSIP Haiphong Integrated Township and Industrial Park
Project. Chairman of Haiphong
People’s Committee Duong Anh Dien attended and chaired the meeting.
5 projects invest in VSIP Haiphong

Such information was exposed at the
annual meeting, held on the
morning of 15th March, for reviewing the development progress of VSIP Haiphong Integrated Township and Industrial Park
Project. Chairman of Haiphong
People’s Committee Duong Anh Dien attended and chaired the meeting.
Up
to now, the project has been handed over 105 ha land to implement phase 1.
Total 4,483 households have received payment of VND 603 billion for
resettlement fee. 7,000 graves in the project area have been relocated. The
resettlement land No.1 was already completed. The resettlement land No.2 is
under construction and about to complete soon. There have been 5 projects which
were issued investment certificates on total area of 50 ha land with total
invested capital of USD 225 billion. Currently, the construction of
infrastructure for the township and industrial park is in progress, in which
114 ha land were already sandfilled; 12 km of roads and infrastructures were already
completed; other works are under construction including VSIP Haiphong Office
Building, 110kV substation, water treatment plant, sewerage treatment plant, etc…
However, the resettlement work is still facing some difficulties, i.e., 8
households have not received payment, 17 households already received payment
but yet relocated, resettlement land projects have taken a lot of time pending
approval of competent authorities, some administrative procedures are also
pending authorities’ approval, etc…
Chairman
of Haiphong People’s Committee Duong Anh Dien appreciated efforts of the
Investor, and expected the Investor to develop VSIP Haiphong into a large
integrated township and industrial park as designed. Chairman requested
competent departments and Thuy Nguyen District to help release difficulties and
obstacles in order for the Investor to speed up progress of the project. As
targeted for the year 2012, VSIP Haiphong will attract about USD 500 million of
foreign investment to the industrial park, which orients to attract Japanese investors
with highly additional value and without causing environmental pollution. The
Investor should conduct a closer and better coordination with Haiphong city in solving arisen issues regarding
to the project, and maintaining a weekly report mechanism…