19/11/2026
Accelerating public investment disbursement
At the recent expanded meeting of the Hai Phong City Party Committee, Secretary of the City Party Committee Le Ngoc Chau directed the city to strive to disburse more than 100% of the public investment capital allocated by the Prime Minister within November, achieving the target two months ahead of the central government's deadline. The city also aims to reach 120% of the Prime Minister's assigned plan by the end of December. To implement this directive, site clearance and accelerating construction progress on key projects are among the crucial measures to achieve the above targets. Our report from the construction project of Ring Road No. 2, the section from Tan Vu through Hung Dao to Bui Vien Street.
Package No. 20 involves the construction of Hai Thanh Bridge and its approach roads. During this final construction phase, the contractor consortium has organized multiple work shifts to complete the remaining items. As a key structure along Ring Road No. 2, Hai Thanh Bridge has been given priority, with contractors mobilizing manpower and machinery to accelerate construction and aiming to complete the bridge's structural connection in November.
According to the city's critical project schedule for the Tan Vu – Hung Dao – Bui Vien Street section of Ring Road No. 2, the road is scheduled to open to traffic on January 31, 2027. Consequently, construction activities across all project packages are being accelerated day by day.
Following the directive of the City Party Committee Secretary at the expanded meeting, local authorities and relevant agencies must review each project, particularly major and high-value key projects, and proactively resolve obstacles related to site clearance, construction and financial settlement within their respective authority.
Ring Road No. 2, one of the five projects subject to the city's special monitoring and supervision, is expected to be fully completed and put into operation on the occasion of April 30.