Speeding Up Progress of Hai Phong International Gateway Port Projects
As one of the prominent projects in the city, the construction of berths at the Hai Phong International Gateway Port project site in Lach Huyen has quickly resumed working right after Storm No. 1. The contractor is taking advantage of favorable weather by focusing on construction and ensuring the schedule.

Hải Phòng có 52 bến cảng thuộc Hệ thống Cảng biển Việt Nam

 

At the project site of berths No. 3 and 4 in Lach Huyen Port, the executor has maintained three shifts all around o’clock. The ground leveling, pile foundation treatment, and other work items have been deployed simultaneously. Having overcome difficulties in construction conditions, the contractor has mobilized all workers and equipment to speed up the construction to ensure progress.

The safety and health of the workers here is also a matter of concern, especially on severe weather days, forcing the workers’ working time to be adjusted to the summer conditions and offshore construction sites.

In the third quarter, the contractor focuses on completing the buffer wharf, piling the entire main port, and building the foundation of berth No. 3. Besides, the investor has embarked on choosing contractors for the remaining equipment packages and tried to complete the appraisal and approval of the electrical system design and the power system, IT system, and items outside the EC bidding package as well as choose suppliers for the above items.